Sitio

Batawa

  • Sitio Canadá
  • Energía Hidroelectricidad
  • Cliente Ontario Electricity Financial Corporation
  • Estado In operation
  • Poner en funcionamiento 1999
  • Vencimiento de PPA 2029
  • Potencia bruta instalada 5
  • Participación Innergex (%) 100
The Batawa Facility draws water from the Trent-Severn Waterway, which has a drainage area of approximately 12,500 square kilometres and comprises Balsam, Sturgeon, Buckhorn, Stony and Rice Lakes. This facility consists of a run-of-river hydroelectric generating station with an installed capacity of 5 MW that holds one double-regulated Kaplan pit-type turbine. The powerhouse is directly hooked to the 44 KV distribution system of Hydro One Networks Inc. The plant is fully automated and may be operated locally or remotely. It is also equipped with a rolling gate, which regularizes the downstream flow from the plant during turbine stops and starts, preventing disruptions of boat traffic. More information about the flow